Jump to content

Yellow line (Stockholm metro)

From Wikipedia, the free encyclopedia
Yellow line
Overview
Native nameGula linjen
LocaleStockholm, Sweden
Termini
Stations6
Websitehttps://nyatunnelbanan.se/en/alvsjo/
Service
TypeRapid transit
SystemStorstockholms Lokaltrafik (SL)
Depot(s)Älvsjö Industrial Area
History
Commenced2025
Planned opening2035
Technical
Line length8 km (5.0 mi)
CharacterUnderground subway and at–grade-separated
Route map

The Yellow Line (Swedish: Gula linjen) is a planned line on the Stockholm metro that will connect Fridhemsplan in the west of central Stockholm to Älvsjö in the southern part of the city. The line is planned to open for service in 2034, and should serve approximately 75,000 passengers per day by 2050.[1]

The line will feature interchanges with all three of the Metro's existing lines, as well as to the Stockholm commuter rail and Tvärbanan light rail, however will be the Metro's first line without a station at T-Centralen.[2]

Preparatory works for the line started in 2024,[3] with construction works scheduled to begin in 2025. The Yellow Line is estimated to cost nearly 14 billion Swedish kronor, with the majority of the funding coming from the state. As a condition of this funding, the City of Stockholm is required to build 48,500 new homes.[4]

History

[edit]

The initiative for a new line to the west of the city centre, avoiding Slussen, began with the Stockholm Negotiations (Swedish: Stockholmsförhandlingen) in 2013, which involved talks between the government, regions, and municipalities on improved public transport and urban development.[5]

In spring 2017, an agreement was reached to build a new line connecting Fridhemsplan and Älvsjö, including a stop at Liljeholmen.[6] Planning for the line began in 2020, including a study to assess potential routes and station locations. Public consultations were held to gather feedback from residents and local authorities.[7] In 2021, the regional council approved a route with six station locations. In 2022, detailed planning and environmental assessments were conducted to outline construction methods and locations. Studies examined the impact on local land use and natural resources.[7]

In May 2023, it was announced that the line would be called the "Yellow Line". Previously, yellow was used for the extension the Green Line from Odenplan to Arenastaden, due to open in 2028. This was rebranded instead as a new branch of the Green Line.[8]

In 2024, preparatory work started, including modifications to existing infrastructure.[3] A permit application for environmental clearance was submitted to the Environmental Court to assess impacts such as groundwater management and noise.[9]

In 2025, plans will be submitted for the line's official approval, and construction is expected to start later that year, pending all necessary permits. The construction phase is projected to last around nine years, with completion expected around 2034.[1]

Route

[edit]
Fridhemsplan Metro Station, the planned Northern terminus of the line

The Yellow Line will be approximately 8 km long, running north to south, to the west of the city centre. The line will include six stations :[1]

The line will run entirely underground, including a section beneath Lake Mälaren. Östbergahöjden was originally planned as "Östberga", but was renamed in April 2024 to avoid confusion with a station on the Roslagsbanan.[10]

Infrastructure

[edit]

The Yellow Line will have several features distinctive from Stockholm's existing metro lines. Unlike the other lines, which feature physical connections, the Yellow Line will be separate from the rest of the metro network.[11] This is due to differences in the line's technologies and a design, including shorter platforms and autonomous train operation.

Älvsjö Station, the planned Southern terminus of the line

Stations

[edit]

Platforms along the line will be built to accommodate 75-metre-long trains, much shorter than the 145-metre platforms on other lines in the Stockholm Metro. The intention is that capacity is instead created by more frequent departures and shorter total travel times.

The six new stations between Fridhemsplan and Älvsjö, will be equipped with lifts designed to transport passengers between the surface and platform levels in 20 to 30 seconds, as the stations will not have escalators. These stations will also feature narrower platform widths, and will be prepared for platform screen doors.[12]

Tunnels

[edit]

The line will be constructed with tunnels reaching a maximum depth of 80 metres below the surface, shallower than initially planned 100-metre depth proposed in earlier designs. Some stations, like Liljeholmen, have seen a significant change, with the station now being 38 metres higher than in earlier plans. This reduction in depth is aimed at lowering construction costs and shortening the project timeline.

Depot

[edit]

The planned depot for the Yellow Line will be located in the Älvsjö industrial area, south of Älvsjö station. It is designed to accommodate approximately 10 trains, and will include maintenance and washing facilities.[13] The depot will include both over-ground and under-ground sections. A connection between the depot and nearby Western Main Line, to facilitate the movement of trains and maintenance vehicles, is being investigated.[14]

Rolling Stock

[edit]
Autonomous train on the Copenhagen Metro

The line will feature unattended autonomous trains, making it the first line in Sweden to use driverless metro technology.[15] The decision was made by Region Stockholm in September 2023. The trains will not have driver cabs, allowing for additional seating and views of the tunnel, similar to the system used in the Copenhagen Metro.[16] Trains will be 70 metres in length, approximately half the length of trains used on other Stockholm Metro lines.[17]

Construction Methods

[edit]

Preparatory works for the line commenced in 2024,[3] and construction of the Yellow Line is set to begin in 2025. The project will employ two tunnel boring machines (TBMs) to excavate bedrock for the two tunnels in parallel, a method that aims to reduce disruptions and speed up the construction process compared to the traditional drill-and-blast technique used in other Stockholm metro expansions.[18] Blasting will still be used for the creation of station spaces and vertical access shafts. In May 2024, plans for a controversial work tunnel originally planned near Rålambshovsparken were scrapped, and relocated to Lindhagensplan.[19]

See also

[edit]

References

[edit]
  1. ^ a b c "Stockholm Metro Expansion, Sweden". Railway Technology. Retrieved 2024-09-24.
  2. ^ "Så stora blir tidsvinsterna med nya tunnelbanan". DN.se (in Swedish). 2023-09-22. Retrieved 2024-09-25.
  3. ^ a b c "Förberedande arbeten". Nya tunnelbanan (in Swedish). Retrieved 2024-09-24.
  4. ^ "Sweco Group - New metro line Fridhemsplan – Älvsjö in Stockholm". Sweco Group. Retrieved 2024-09-24.
  5. ^ Nyheter, S. V. T. (2014-04-10). "Regeringen godkände finansiering av mer tunnelbana". SVT Nyheter (in Swedish). Retrieved 2024-09-24.
  6. ^ Majlard, Jan (2019-10-31). "Största satsningen sedan 70-talet – på 3 minuter". Svenska Dagbladet (in Swedish). ISSN 1101-2412. Retrieved 2024-09-24.
  7. ^ a b "Tidplan". Nya tunnelbanan (in Swedish). 2021. Retrieved 2024-09-24.
  8. ^ Nyheter, S. V. T. (2023-05-17). "Gult blir grönt när tunnelbanan byggs ut". SVT Nyheter (in Swedish). Retrieved 2024-09-24.
  9. ^ neighborhood, Better (2023-12-30). "1000 synpunkter på nya tunnelbanan till Älvsjö – detta väckte mest kritik - BÄTTRE STADSDEL". BÄTTRE STADSDEL - Lokal nyhetsbyrå i Stockholm. Retrieved 2024-09-24.
  10. ^ "Namnbyte av tunnelbanans station i Östberga". www.jarnvagsnyheter.se (in Swedish). Retrieved 2024-09-24.
  11. ^ Engström, Henrik (2023-09-27). "The yellow line is planned for unattended train operation". Nya tunnelbanan. Retrieved 2024-09-24.
  12. ^ "Tunnelbana till Älvsjö - Sammanställning och bemötande av inkomna synpunkter i samrådsprocessen" (PDF). nyatunnelbanan.se. 2024-04-25.
  13. ^ "Älvsjö föreslås som plats för ny tunnelbanedepå". www.jarnvagsnyheter.se (in Swedish). Retrieved 2024-09-24.
  14. ^ "Ny depå i Älvsjö industriområde". Nya tunnelbanan (in Swedish). Retrieved 2024-09-24.
  15. ^ "Gula t-banelinjen får förarlösa tåg". DN.se (in Swedish). 2023-09-26. Retrieved 2024-09-24.
  16. ^ MattssonText, Per (2023-10-04). "Beslutat: Gula linjen i Stockholm får förarlösa tåg". Dagens industri (in Swedish). Retrieved 2024-09-24.
  17. ^ "Stockholm orders more C30 metro trains". International Railway Journal. March 11, 2024.
  18. ^ Nyheter, S. V. T. (2024-05-21). "Tunnelbanans gula linje ska byggas med gigantiska tunnelborrar". SVT Nyheter (in Swedish). Retrieved 2024-09-24.
  19. ^ "Stopp för tunnelbygge i Rålambshovsparken". DN.se (in Swedish). 2024-05-22. Retrieved 2024-09-24.