Fangchenggang Nuclear Power Plant
Fangchenggang Nuclear Power Plant | |
---|---|
Country | People's Republic of China |
Location | Hongsha, Gangkou, Fangchenggang, Guangxi |
Coordinates | 21°40′15″N 108°33′30″E / 21.67083°N 108.55833°E |
Status | Operational |
Construction began | 30 July 2010 |
Commission date | 1 January 2016 |
Operator | Guangxi Fangchenggang Nuclear Power Group |
Nuclear power station | |
Reactor type | CPR-1000, HPR-1000 |
Cooling source | Gulf of Tonkin |
Power generation | |
Units operational | 4 × 1,000 MW |
Units planned | 2 × 1000 MW |
Nameplate capacity | 4,000 MW |
Fangchenggang Nuclear Power Plant (simplified Chinese: 防城港核电站; traditional Chinese: 防城港核電站; pinyin: Fángchénggǎng hédiànzhàn), also known as Fangchenggang Hongsha Nuclear Power Plant (simplified Chinese: 防城港红沙核电站; traditional Chinese: 防城港紅沙核電站), is a nuclear power plant in Fangchenggang, near Hongsha Village(simplified Chinese: 红沙村; traditional Chinese: 紅沙村),[1] autonomous region of Guangxi (Guangxi Zhuang Autonomous Region) in the People's Republic of China. A total of six reactors are planned to operate at the Fangchenggang site. Units 1 and 2 are both CPR-1000s, units 3–4 are Hualong Ones, units 5–6 are planned also to be Hualong One reactors. Fangchenggang 3 and 4 will be the reference plant for the proposed Bradwell B plant in the UK.[2]
The plant is located about 54 kilometres from the border with Vietnam. It is a project of Guangxi Fangchenggang Nuclear Power Group, a joint venture between China Guangdong Nuclear Power Co (CGNPC) and Guangxi Investment Group.[3]
Unit 1 was connected to the electricity grid on 25 October 2015.[4] Unit 1 is commercially operating starting on 1 January 2016. [5]
Construction works for Unit 3 started in December 2015.[6] Unit 3 first concrete pour occurred on 24 December 2015.[7] First concrete for Unit 4 followed one year later, on 23 December 2016.[8]
Reactor data
[edit]The Fangchenggang Nuclear Power Plant consist of 4 operational reactors and 2 reactors planned.
Unit | Type /Model | Net power |
Gross power |
Thermal power |
Construction start |
First criticality |
Grid connection |
Operation start |
Notes |
---|---|---|---|---|---|---|---|---|---|
Phase I | |||||||||
Fangchenggang 1 | PWR / CPR-1000 | 1000 MW | 1086 MW | 2905 MW | 2010-07-30 | 2015-10-13 | 2015-10-25 | 2016-01-01 | [9] |
Fangchenggang 2 | PWR / CPR-1000 | 1000 MW | 1086 MW | 2905 MW | 2010-12-23 | 2016-06-29 | 2016-07-15 | 2016-10-01 | [10] |
Phase II | |||||||||
Fangchenggang 3 | PWR / HPR1000 | 1000 MW | 1180 MW | 3150 MW | 2015-12-24 | 2022-12-27 | 2023-01-10 | 2023-03-25 | [11] [12] |
Fangchenggang 4 | PWR / HPR1000 | 1000 MW | 1180 MW | 3150 MW | 2016-12-23 | 2024-04-03 | 2024-04-09 | 2024-05-25 | [13] |
Fangchenggang 5 | PWR / HPR1000 | 1000 MW | 1180 MW | 3150 MW | [14] | ||||
Fangchenggang 6 | PWR / HPR1000 | 1000 MW | 1180 MW | 3150 MW | [14] |
See also
[edit]References
[edit]- ^ "China's Fangchenggang: natural beauty and port economy". Sino-US.com. 9 June 2013. Archived from the original on 2 April 2019. Retrieved 20 September 2019.
- ^ "Chinese firms join forces to market Hualong One abroad". World Nuclear News. 31 December 2015. Retrieved 4 January 2016.
- ^ "Construction of Fangchenggang plant starts". World Nuclear News. 3 August 2010. Retrieved 4 January 2016.
- ^ "First Fangchenggang unit connected to grid". World Nuclear News. 26 October 2015. Retrieved 6 February 2016.
- ^ "FANGCHENGGANG-1 Operational Details". International Atomic Energy Agency. 1 January 2016. Retrieved 6 February 2016.
- ^ "Fangchenggang Nuclear Power Plant, Guangxi, China". Kable Intelligence Limited. Retrieved 6 February 2016.
- ^ "CGN's Fangchenggang-3 begins construction with first concrete pour". China General Nuclear Power Corporation. 24 December 2015. Archived from the original on 6 February 2016. Retrieved 6 February 2016.
- ^ "Construction starts on second Hualong One". World Nuclear News. 29 December 2016. Retrieved 8 January 2017.
- ^ "Fangchenggang 1". Power Reactor Information System (PRIS). International Atomic Energy Agency (IAEA). 2016-10-24. Retrieved 25 October 2016.
- ^ "Fangchenggang 2". PRIS. IAEA. 2016-10-24. Retrieved 25 October 2016.
- ^ "Fangchenggang 3". PRIS. IAEA. 2016-10-24. Retrieved 25 October 2016.
- ^ "中广核广西防城港核电站3号机组首次并网发电". www.cnnpn.cn. Retrieved 2023-01-10.
- ^ "Fangchenggang 4". PRIS. IAEA. 2017-01-07. Retrieved 8 January 2017.
- ^ a b "Nuclear Power in China". Country Briefings. World Nuclear Association (WNA). December 2016. Retrieved 8 January 2017.